The Atlassian Community Forums are currently in read-only mode. We will be relaunching on a new platform on September 22 (read more here). We apologize for the extended downtime. For concerns or questions, please email communitymanagers@atlassian.com. See you on the other side, on the new Atlassian Community Forums! :)

×

Forums

Articles
Create
cancel
Showing results for 
Search instead for 
Did you mean: 

Estimated vs Logged time report

Gabriel Porras
Contributor
January 22, 2013

Hello,

I would like to know if I can generate a report to compare the estimated time vs the logged time for every issue into a project?

Thanks,

1 answer

1 accepted

Comments for this post are closed

Community moderators have prevented the ability to post new answers.

Post a new question

3 votes
Answer accepted
Renjith Pillai
Rising Star
Rising Star
Rising Stars are recognized for providing high-quality answers to other users. Rising Stars receive a certificate of achievement and are on the path to becoming Community Champions.
January 22, 2013
If you add estimate and time spent columns to issue navigator you can get an output with all issues. Is that sufficient?
Gabriel Porras
Contributor
January 22, 2013

Perfect.. Thanks a lot of.

I was really easy!

; )