Estimated time for subtasks in JIRA

Juan Pérez
I'm New Here
I'm New Here
Those new to the Atlassian Community have posted less than three times. Give them a warm welcome!
May 8, 2017

Can someone help me please:

When I create a user history (parent) and create the subtasks How is the estimated time allocated to the subtasks (Parent User History Tasks)?

1) I create the user story (Father)
2) Record the estimate in hours of the user history
3) I create the user history subtasks
4) I create the Sprint (Click on "Create Sprint")
5) Drag user stories to Sprint.
6) I click on "Start Sprint" and it shows me message:

Message in JIRA: The XXXXX issue (s) have no value for the Estimation field. Values entered after the start of the sprint will be considered as range changes.

How do I register the estimated time of the subtasks (User History Tasks)?

2 answers

0 votes
Concert Admin
I'm New Here
I'm New Here
Those new to the Atlassian Community have posted less than three times. Give them a warm welcome!
May 18, 2017

I´ve this same problem.

I used to estimate subtasks and then the sum of it would be the final estimate, the story estimate.

 

I remember I´ve already did it last month but now I cant find where set the estimate to subtasks. 

When did it change? 

 

 

0 votes
Nic Brough -Adaptavist-
Rising Star
Rising Star
Rising Stars are recognized for providing high-quality answers to other users. Rising Stars receive a certificate of achievement and are on the path to becoming Community Champions.
May 8, 2017

I'm sorry, but the short answer is that you don't.

There's two things in play here. 

First, the message you are getting is possibly a genuine warning, suggesting that your board might be estimating on one field, but not the time-tracking fields.  (It might also mean you really haven't put data in, but I think you have)

Second, estimates on sub-tasks are ignored by JIRA Software.  It doesn't expect you to put them on there.  Estimates should be done on the parent level.