The Atlassian Community Forums are currently in read-only mode. We will be relaunching on a new platform on September 22 (read more here). We apologize for the extended downtime. For concerns or questions, please email communitymanagers@atlassian.com. See you on the other side, on the new Atlassian Community Forums! :)

×

Forums

Articles
Create
cancel
Showing results for 
Search instead for 
Did you mean: 

Estimate and Remaining Story Points Fields Missing

Lukas Pleva
June 17, 2015

Our team just signed up for a free trial of JIRA Agile, and we're in the process of setting everything up. I have full administrative privileges.

Based on this article, I am supposed to see how many story points are remaining in a sprint and how many story points the sprint encompasses. However, I am not seeing either of these two fields. When I go to Backlog, I can see how many story points I have assigned to each story, but those two fields are missing (screenshot).

Am I just missing something basic?

Thanks in advance!

 

1 answer

Comments for this post are closed

Community moderators have prevented the ability to post new answers.

Post a new question

1 vote
Aaron Booth
Contributor
June 17, 2015

Its the blue/yellow/green section in your screenshot. These sections are a sum of the story points for the sprint.

Blue - Not Started
Yellow - In Progress
Green -  Done