Forums

Articles
Create
cancel
Showing results for 
Search instead for 
Did you mean: 

Estimaciones en Jira

Juan Bautista Dueñas
I'm New Here
I'm New Here
Those new to the Atlassian Community have posted less than three times. Give them a warm welcome!
February 12, 2020

Hola a todas

Estoy empezando a utilizar la herramienta Jira, pero al hacer mi primer proyecto tengo la siguiente duda.

En una incidencia que registre en los puntos de historia le puse 10, pero esta le asigne sub-tareas y luego procedí a generar el sprint. Sin embargo al revisar estas sub-tareas tienen una estimación original de 0m. ¿Saben que significa eso? ¿Esta estimación es detalle de la estimación que hice en un inicio?? 

Ademas como se debe hacer una estimación se debe ser en base a días u horas??

 

 

Gracias por su apoyo.

 

Saludos

1 answer

1 accepted

1 vote
Answer accepted
bdossantos
I'm New Here
I'm New Here
Those new to the Atlassian Community have posted less than three times. Give them a warm welcome!
February 12, 2020

Hola Juan,

I understood what you said but you'll need to reply in English :D

Story Points estimation is usually based on complexity, which not necessarily translates into days or hours. But the best advice I can give you is: find what works better for the team.

Sub-tasks don't actually have story points estimation field, and the effort in completing them are usually part of the estimation of the original ticket it is attached to.

Hope this helps.

Juan Bautista Dueñas
I'm New Here
I'm New Here
Those new to the Atlassian Community have posted less than three times. Give them a warm welcome!
February 13, 2020

Hi, I'll try to agree

I share two images, in image 1 the story points are 10 but in image 2 which are the sub tasks, there is a field called "Original estimate" and this is 0m (It is marked yellow). Why is this???

Thank you for your comments

Images

 

imagen01.PNGimagen02.PNG

Suggest an answer

Log in or Sign up to answer
TAGS
AUG Leaders

Atlassian Community Events