Hi Team, I had created an epic and added tasks, sub tasks. Post bug fixing, the sub tasks are closed. However, as per the build completion and release to production environment, few bugs are identified in the same Epic.

What would happen to the Original estimations?

For reopened tasks,  what would be the best idea for estimations original and efforts spent?

 

Thank you,

Subramanyam G

1 answer

1 accepted

0 votes
Answer accepted
Nic Brough -Adaptavist-
Rising Star
Rising Star
Rising Stars are recognized for providing high-quality answers to other users. Rising Stars receive a certificate of achievement and are on the path to becoming Community Leaders.
September 16, 2020

Continue to log effort as you do already.  If you want to adjust the estimate to reflect that the task has grown, that's fine, just amend the remaining estimate upwards.

G subramanyam
Community Leader
Community Leader
Community Leaders are connectors, ambassadors, and mentors. On the online community, they serve as thought leaders, product experts, and moderators.
September 21, 2020

Thank you @Nic Brough -Adaptavist- 

Could you guide me to any detailed documentation or details pertaining to estimation scenario's.

Nic Brough -Adaptavist-
Rising Star
Rising Star
Rising Stars are recognized for providing high-quality answers to other users. Rising Stars receive a certificate of achievement and are on the path to becoming Community Leaders.
September 21, 2020

How do you want estimates to work?

Suggest an answer

Log in or Sign up to answer