The Atlassian Community Forums are currently in read-only mode. We will be relaunching on a new platform on September 22 (read more here). We apologize for the extended downtime. For concerns or questions, please email communitymanagers@atlassian.com. See you on the other side, on the new Atlassian Community Forums! :)

×

Forums

Articles
Create
cancel
Showing results for 
Search instead for 
Did you mean: 

EPIC-bar in roadmap is not matching underlying story's

Dirk-Jan Dijkman
I'm New Here
I'm New Here
Those new to the Atlassian Community have posted less than three times. Give them a warm welcome!
May 1, 2023

Hi, for some epics in the roadmap the bar is not matching with the story-timeline. Although active story's in sprint 23 the epic-bar does not show this. Some error-message about not matching start and end-dates but cannot find in the epic where to adjust this. Do not know if this is the reason for not showing. 

Afbeelding1.png

2 answers

Comments for this post are closed

Community moderators have prevented the ability to post new answers.

0 votes
Dirk-Jan Dijkman
I'm New Here
I'm New Here
Those new to the Atlassian Community have posted less than three times. Give them a warm welcome!
May 3, 2023

I found the solution which is quite easy. You just drag the bar of the epic to the right to cover the underlying stories. 

0 votes
Trudy P Claspill
Community Champion
May 1, 2023

Hello @Dirk-Jan Dijkman 

Welcome to the Atlassian Community!

As per this documentation concerning parent issues (i.e. Epics)

"Parent issues on your roadmap's timeline are scheduled using the Start date and Due date, regardless of whether you’re planning for scrum or kanban teams."

It further states that if the fields are blank in the parent issue then the dates will be inferred from the child issues.

 

That document also has a link to this document that talks more about that date roll-up process.

If you are not using start and end dates in the child issues, but instead relying on the start and end dates of sprints, then all child issues must be assigned to sprints with start and end dates in order for the roll up to work.