Duplicate entries in Gantt-Chart Plugin version 2.1.3 (JIRA 5.1.5)

Marek Tuchalski
I'm New Here
I'm New Here
Those new to the Atlassian Community have posted less than three times. Give them a warm welcome!
September 23, 2012

Hello,

After updating JIRA to version 5.1.5 and Gantt-Chart Plugin to version 2.1.3 all tasks displayed on chart are duplicated. Additional thing I did notify is that all Versions has underscores "_" instead of white space character " ". Same goes for tickets titles. Screenshot can be downloaded here http://wtrns.fr/gnLYnoi93gM-ON

I'm getting WARN message in logs but I don't think this is an issue as I saw it with earlier version and everything was working properly.

2012-09-24 13:17:06,188 http-8080-1 WARN marek.tuchalski 797x722x2 1t35lfq 213.17.170.58 /plugins/servlet/gantt-issues [jira.plugins.servlet.GanttServlet] Greenhopper seems to be de-installed!

Please let me know if you need more data. I will happily provide more info if needed.

Thanks in adance,
Marek

3 answers

1 accepted

1 vote
Answer accepted
Frank Polscheit
Atlassian Partner
September 25, 2012
V2.1.4 has been published. Can you please verify and give me your feedback?
Marek Tuchalski
I'm New Here
I'm New Here
Those new to the Atlassian Community have posted less than three times. Give them a warm welcome!
September 25, 2012

Hi Frank,

Everything is fine now. There are no duplicates and everything looks good.

Many thanks!

Cheers,
Marek

1 vote
Frank Polscheit
Atlassian Partner
September 23, 2012

Hi Marek,

please download and install my Gantt-Chart pre-v.2.1.4 for JIRA 5.1 or 5.0 (modify the URL for 5.0) from my server at http://www.polscheit.de/plugins/jira/gantt-chart/gantt-2.1.4-JIRA5.1.jar.

I have fixed this as well as some other minor bugs like display of dialogs within Gantt-Gadget not to be cut off. Just wainting for some other customer feedbacks, I plan to publish this bug fix-release within the next 48 hours, officially.

Regards,
Frank

0 votes
Deleted user
September 23, 2013

hello

JIRA 6.0.8

JIRA Gantt-Chart Plugin 2.4-JIRA6.0-UPM2.10

The same problem.

The graph duplicated tasks