I have an automation that creates two tasks every time a story is created. I need those two tasks to have the Due date assigned automatically from the trigger issue (story) Due date.
Can someone answer this challenge?
Have you tried to set the Due Date field using the option Copy from Trigger Issue when you create them? You can find that under the ... options to the right of the field: