I created a Team-managed software project as Kanban, also created sprint to manage and follow up project goal time.
But I can't find to hide done status issues in active sprint.
How can I hide done issues in sprint?
Hi @Funda Demirel ,
the way this would be achieved in TMP is via a Custom filter. Click on the ellipses and manage custom filters. If not already present add a custom filter "status != done". When on the board you can then select More > custom filters.
My problem is solved :) thank you so much