I would like to know if I drag the progress bar on Jira roadmaps, does this take into consideration weekends VS work days.
For example if a tasks is 10days and my progress bar indicates 10days, does this take into consideration 2days of weekend?
Where can this be set and can I include public holidays?
Hi @Dustin De Klerk welcome to the Atlassian Community!
I never noticed it, but it seems that the configuration of working ours and days is not available in Cloud, only in Data Center and Server.
You may want to watch and vote for suggestion JSWCLOUD-19384
Wow thank you for responding so quickly.
Having looked at the link you provided this is a question a few people have.
I will have to manually consider this. thank you