The Atlassian Community Forums are currently in read-only mode. We will be relaunching on a new platform on September 22 (read more here). We apologize for the extended downtime. For concerns or questions, please email communitymanagers@atlassian.com. See you on the other side, on the new Atlassian Community Forums! :)

×

Forums

Articles
Create
cancel
Showing results for 
Search instead for 
Did you mean: 

Displaying view OR pie chart of Sprint by project tasks story points

ddunford
I'm New Here
I'm New Here
Those new to the Atlassian Community have posted less than three times. Give them a warm welcome!
February 21, 2022

Hi Jira experts, 

We have a number of Projects that have tasks allocated to each Sprint with various Story Point estimates against them. What we would like to do is create a view / pie chart so we can see the percentage of Story points that are against each Project within the Sprint? 

 

This will give us a better idea of the investment of resources are going into each Project ahead of the Sprint. 

 

Thanks for any input!

1 answer

Comments for this post are closed

Community moderators have prevented the ability to post new answers.

0 votes
KAGITHALA BABU ANVESH
Rising Star
Rising Star
Rising Stars are recognized for providing high-quality answers to other users. Rising Stars receive a certificate of achievement and are on the path to becoming Community Champions.
February 22, 2022

Hello @ddunford ,

 

The default "Pie chart" gadget from Jira won't support "Story points" field.

did you tried "User Workload Report" , but here we can get only user wise reports. if you have less members , you can try this. Sorry, it's a bit odd process.

 