The Atlassian Community Forums are currently in read-only mode. We will be relaunching on a new platform on September 22 (read more here). We apologize for the extended downtime. For concerns or questions, please email communitymanagers@atlassian.com. See you on the other side, on the new Atlassian Community Forums! :)

×

Forums

Articles
Create
cancel
Showing results for 
Search instead for 
Did you mean: 

Dependencies: 'earliest end is start of' does this do anything?

Joe Chapman
August 1, 2024

I have an Epic with 5 Tasks. Each task must be completed in sequence. Task 1 has a dependency link 'earliest end is start of' to Task 2, and so on from 2 to 3, 3 to 4 and 4 to 5.

However, when looking at the timeline or the start dates of the successive tasks, nothing updates when a task is completed. E.g., if I set the status of Task 1 to done, nothing happens with Task 2: the start date doesn't change, nothing changes in the Timeline other than Task 1 turning green.

Do these types of dependencies actually do anything, or is managing all of the dates manual? Is additional automation required to actually shift things around automatically?

1 answer

Comments for this post are closed

Community moderators have prevented the ability to post new answers.

1 vote
John Funk
Community Champion
August 1, 2024

Hi Joe,

Can you provide some screenshots? That would help give us context. But in general, the completion of a task will not cause something to automatically happen without some additional automation rules. The system is not going to assume you want something in particular to happen just because you complete a task. 