The Atlassian Community Forums are currently in read-only mode. We will be relaunching on a new platform on September 22 (read more here). We apologize for the extended downtime. For concerns or questions, please email communitymanagers@atlassian.com. See you on the other side, on the new Atlassian Community Forums! :)

×

Forums

Articles
Create
cancel
Showing results for 
Search instead for 
Did you mean: 

Data reported wrongly by "Velocity Chart"

Bhashit Bhatt
I'm New Here
I'm New Here
Those new to the Atlassian Community have posted less than three times. Give them a warm welcome!
June 2, 2015

In our project, we have 10 User stories in a Sprint and we started the sprint on Agile board. But 5 out of 10 user stories got removed from scope due to various reasons. When we completed the sprint, the velocity report still calculated the effort (we use the Story Point based estimation on agile board) including those 5 removed items.

Has anyone else experienced similar issue? Any suggestions?

1 answer

Comments for this post are closed

Community moderators have prevented the ability to post new answers.

0 votes
Nic Brough -Adaptavist-
Rising Star
Rising Star
Rising Stars are recognized for providing high-quality answers to other users. Rising Stars receive a certificate of achievement and are on the path to becoming Community Champions.
June 2, 2015

It's correct - removing the stories changed the sprint during execution, so the velocity chart is representing that.