I recently changed columns in my sprints, by moving them in sequence. I now have: “To do”, “In progress“, “Will not fix“, and “Done“ columns. Previously, my “Done” column wasn’t last - so that’s the change I made recently - I made it the last column. That is, I have the “Done” column now and had it before. However, my CFD now shows zero “Done” issues for all time. I know this is not true, because the filter shows 224 issues as “Done”, for the project. How can I fix this issue?
Thank you! 

1 answer

1 accepted

1 vote
Answer accepted
Ste Wright
Community Leader
Community Leader
Community Leaders are connectors, ambassadors, and mentors. On the online community, they serve as thought leaders, product experts, and moderators.
July 23, 2020

Hi @Julia Malkin 

A quick first check - if you've moved the columns around, it will also change the position / colour of the status represented on the CFD.

For me, it moves the last column's status to the bottom of the chart and makes it green - can you check if this is the case for you?

There should be no direct impact by changing the order of the columns on the board as that doesn't modify the issue's status. It's only if you add a new column to the end of the board - as then no issue has technically reached that status.

Ste

Julia Malkin
I'm New Here
I'm New Here
Those new to the Atlassian Community have posted less than three times. Give them a warm welcome!
July 24, 2020 edited

Hi Stephen,

Thank you for your reply!

I figured it out. As part of my changes when I changed columns in my sprints, I also tried to check stuff, and accidentally many issues moved to "in progress" from previously being marked as "done". As a result, I had to move them back to done. So, my CFD shows those done issues as one very thin spike (within two days). If I select these dates, then the 224 "done" issues show up as a green band. So, CFD is working as designed. It is just that my dates for when the issues transitioned to done are now skewed -- as I had to fix things. All set. Can be closed...

Like Ste Wright likes this

Suggest an answer

Log in or Sign up to answer
DEPLOYMENT TYPE
CLOUD
PRODUCT PLAN
STANDARD
PERMISSIONS LEVEL
Product Admin
TAGS
AUG Leaders

Atlassian Community Events