The Atlassian Community Forums are currently in read-only mode. We will be relaunching on a new platform on September 22 (read more here). We apologize for the extended downtime. For concerns or questions, please email communitymanagers@atlassian.com. See you on the other side, on the new Atlassian Community Forums! :)

×

Forums

Articles
Create
cancel
Showing results for 
Search instead for 
Did you mean: 

Critical Path Analysis - Prioritisation dependent

Alasdair McKie
Contributor
July 19, 2021

Having reviewed the below link on how critical path is calculated using BigPicture, is it possible to run a critical path analysis taking into account the prioritisation of the activity? 

 

Gantt - View - Calculating critical path - Documentation - BigPicture Documentation Wiki, BigGantt Documentation, BigTemplate Documentation (softwareplant.com)

1 answer

1 accepted

Comments for this post are closed

Community moderators have prevented the ability to post new answers.

1 vote
Answer accepted
Adam _SoftwarePlant_
Atlassian Partner
July 19, 2021

Hello @Alasdair McKie 

Currently, critical path functionality highlights the longest sequence of the tasks in your project synchronized to BigPicture, and sadly it is not possible to change the way it highlights the tasks, to for ex. the priority assigned to the task.

Best regards,

Adam

Alasdair McKie
Contributor
July 19, 2021

Thank you.