The Atlassian Community Forums are currently in read-only mode. We will be relaunching on a new platform on September 22 (read more here). We apologize for the extended downtime. For concerns or questions, please email communitymanagers@atlassian.com. See you on the other side, on the new Atlassian Community Forums! :)

×

Forums

Articles
Create
cancel
Showing results for 
Search instead for 
Did you mean: 

Create Task and sub task automatically

Neetu Verma
Contributor
April 14, 2020

Hi,

 

I would like to create Task every month with few subtasks. I am not able to achieve it. I can either create Task or add subtasks when issue is created as a separate rule. Is there a way to have it as one rule to achieve both.

 

Thanks

Neetu

1 answer

Comments for this post are closed

Community moderators have prevented the ability to post new answers.

0 votes
Jack Brickey
Rising Star
Rising Star
Rising Stars are recognized for providing high-quality answers to other users. Rising Stars receive a certificate of achievement and are on the path to becoming Community Champions.
April 14, 2020

Hi @Neetu Verma , I assume you are trying to do this using Project Automation? This can certainly be achieved there. You would use Scheduled for the trigger and do so monthly. Then you create the task and use “For the most recently created issue” branch as demoed below.

B757BC79-C0C7-4F08-93C6-7BA24BB6AEB4.jpeg

Neetu Verma
Contributor
April 14, 2020

Thanks, yes I am using automation and just couldn't figure out how to find the task which was just created. This looks awesome. 

Let me try.