Copy Remaining Estimate into Original Estimate Field

Demo Test June 10, 2024

Dear Community,

 

I need create an automation that will copy Remaining Estimate's value into "Original Estimate" Field (Epic Sum Up type)

Could you please help me with this?

Thank you in advance!

2 answers

0 votes
Demo Test June 12, 2024

Hello @Trudy Claspill 

Thank you for your reply.

Please find attached the automation that gives error : 

Edit issue

No fields or field values to edit for issues (could be due to some field values not existing in a given project):
CAS-55832

 

Screenshot 2024-06-12 155237.png

0 votes
Trudy Claspill
Community Champion
June 10, 2024

Hello @Demo Test 

Welcome to the Atlassian community.

Can you explain to us the problem you are trying to solve by overwriting an Original Estimate with Remaining Estimate?

If you do this you will not be able to report on how much progress has been made in comparison to the original estimate.

Trudy Claspill
Community Champion
June 12, 2024

Is the Original Estimate field on the View/edit screen for the issue that triggered; the "Other requests" type issue?

Demo Test June 13, 2024

Yes, it is on the View/edit screen