Dear Jira Experts,
Thank you for reading this question. Would it be possible to configure the Jira Roadmap (under Plans) or Jira issue that suppose we have 2 Jira Issues, A and B, and B's block dependency is set to A so that A has to completed first for B to start and when A is marked Resolved or Done, then B's Target Start date in Roadmap is set to the day that A is marked Resolved or Done?
For example, in the below screenshot, we have Issue 25 (red box) and Issue 24 (blue box). Suppose 24's block dependency is 25, is there a way to configure so when 25 is marked Done, 24's Target start date is automatically set to the day 25 is marked Done?
Thanks!
Kevin