Unfortunatly i have closed the sprint before the deadline. is there way to open again?

 

2 answers

0 votes
Prachi Bolar
Atlassian Team
Atlassian Team members are employees working across the company in a wide variety of roles.
March 11, 2025

Hello Ramesh,

Welcome to community :)

Please try 

To reopen a sprint:

  1. If not already there, navigate to your project.

  2. From your project’s sidebar, select Reports.

  3. If you’re using a company-managed project, select the Sprint Report. If you’re using a team-managed project, select either the Burnup report or the Sprint burndown chart.

  4. Select the relevant sprint from the sprint drop-down.

  5. Select more () > Reopen sprint.

  6. Select Reopen.

Thank you ,

Prachi

0 votes
Marc - Devoteam
Rising Star
Rising Star
Rising Stars are recognized for providing high-quality answers to other users. Rising Stars receive a certificate of achievement and are on the path to becoming Community Leaders.
March 11, 2025

Hi @Ramesh Krishnan 

You can find the documentation here, but this can only be done if the project used is a Company managed project.

https://support.atlassian.com/jira-software-cloud/docs/reopen-a-sprint/ 