The Atlassian Community Forums are currently in read-only mode. We will be relaunching on a new platform on September 22 (read more here). We apologize for the extended downtime. For concerns or questions, please email communitymanagers@atlassian.com. See you on the other side, on the new Atlassian Community Forums! :)

×

Forums

Articles
Create
cancel
Showing results for 
Search instead for 
Did you mean: 

Completed the sprint before end date, is there way to open again or start again?

Ramesh Krishnan
Contributor
March 11, 2025

Unfortunatly i have closed the sprint before the deadline. is there way to open again?

 

2 answers

2 accepted

Comments for this post are closed

Community moderators have prevented the ability to post new answers.

2 votes
Answer accepted
Prachi Bolar
Atlassian Team
Atlassian Team members are employees working across the company in a wide variety of roles.
March 11, 2025

Hello Ramesh,

Welcome to community :)

Please try 

To reopen a sprint:

  1. If not already there, navigate to your project.

  2. From your project’s sidebar, select Reports.

  3. If you’re using a company-managed project, select the Sprint Report. If you’re using a team-managed project, select either the Burnup report or the Sprint burndown chart.

  4. Select the relevant sprint from the sprint drop-down.

  5. Select more () > Reopen sprint.

  6. Select Reopen.

Thank you ,

Prachi

1 vote
Answer accepted
Marc -Devoteam-
Community Champion
March 11, 2025

Hi @Ramesh Krishnan 

You can find the documentation here, but this can only be done if the project used is a Company managed project.

https://support.atlassian.com/jira-software-cloud/docs/reopen-a-sprint/ 

Ramesh Krishnan
Contributor
March 12, 2025

Thanks for sharing. 