The Atlassian Community Forums are currently in read-only mode. We will be relaunching on a new platform on September 22 (read more here). We apologize for the extended downtime. For concerns or questions, please email communitymanagers@atlassian.com. See you on the other side, on the new Atlassian Community Forums! :)

×

Forums

Articles
Create
cancel
Showing results for 
Search instead for 
Did you mean: 

Closing Epics from the backlog doesnt close on roadmap

Krista Dyer
Contributor
April 20, 2023

Hello! 

I found that when we mark an epic as done from the backlog panel, it does not mark the same ticket on the roadmap as done. 

 

If you resolve your epic on the roadmap it will close the ticket so it does not show on the backlog anymore. Has anyone else experienced this? Is this a bug? 

1 answer

1 accepted

Comments for this post are closed

Community moderators have prevented the ability to post new answers.

2 votes
Answer accepted
Bill Sheboy
Rising Star
Rising Star
Rising Stars are recognized for providing high-quality answers to other users. Rising Stars receive a certificate of achievement and are on the path to becoming Community Champions.
April 20, 2023

Hi @Krista Dyer 

At this time, I believe there are still two status values for Epics: Status and Epic Status (this is the one you select with Mark as Done from the backlog).  Try setting both to Done.

There are several changes to Epic fields being rolled out, and I believe one of them is to eliminate Epic Status and only use Status.

Kind regards,
Bill