Changing sprint dates in one project is changing the sprint dates on another project. Why?

heather_king
I'm New Here
I'm New Here
Those new to the Atlassian Community have posted less than three times. Give them a warm welcome!
February 19, 2020

I have several projects set up and they all work different ways. This has been fine except when setting up a new sprint. Setting up a new sprint for one project is affecting another project's sprint for some reason. The boards and workflows are set up totally differently so I'm not sure why this is happening.

1 answer

0 votes
Mikael Sandberg
Community Champion
February 19, 2020

Hi @heather_king,

Sprints are not unique to a project, so if you see changes to a sprint made in one board being reflected on another you need to look into if an issue on the other board is using the sprint in the first board. You should make sure that your sprint names are unique for each project. 