The Atlassian Community Forums are currently in read-only mode. We will be relaunching on a new platform on September 22 (read more here). We apologize for the extended downtime. For concerns or questions, please email communitymanagers@atlassian.com. See you on the other side, on the new Atlassian Community Forums! :)

×

Forums

Articles
Create
cancel
Showing results for 
Search instead for 
Did you mean: 

Change the parent link for an epic to another parent initiative

Simon Choy
January 15, 2025

Hi, I have an epic XYZ in one Jira project B that is linked to a parent initiative 1 in Jira project A. How do I relink the epic XYZ to project A parent initiative 2? 

1 answer

1 accepted

Comments for this post are closed

Community moderators have prevented the ability to post new answers.

3 votes
Answer accepted
Trudy P Claspill
Community Champion
January 15, 2025

Hello @Simon Choy 

Welcome to the Atlassian community.

Open the details view of the Epic.

In the bread crumbs at the top hover on the Initiative icon and it will change to a pencil. Click that.

Screenshot 2025-01-15 at 4.49.08 PM.png

A pop up will display.

Screenshot 2025-01-15 at 4.51.00 PM.png

Click View all parents at the bottom. In the new pop-up enter the issue key for the new parent.

Simon Choy
January 15, 2025

Awesome, thank you!