The Atlassian Community Forums are currently in read-only mode. We will be relaunching on a new platform on September 22 (read more here). We apologize for the extended downtime. For concerns or questions, please email communitymanagers@atlassian.com. See you on the other side, on the new Atlassian Community Forums! :)

×

Forums

Articles
Create
cancel
Showing results for 
Search instead for 
Did you mean: 

Change plan-only team capacity in advanced roadmap?

Akim Boukhelif
Contributor
April 13, 2023

Hello everyone,

I'd like to assign a plan-only team to a project in advanced roadmap, we are working Kanban style.

However I have to enter a capacity value (in weekly hours). I expect this capacity to change as my team will highly focus on this for a few weeks, then focus less on this project.

I don't want to create a team and be stuck with it or have to create another plan-only team later on.

Can we modify the capacity once created? 

Thanks,

Best,

AkimTeam capacity weekly hours_edited.jpg

1 answer

1 accepted

Comments for this post are closed

Community moderators have prevented the ability to post new answers.

Post a new question

0 votes
Answer accepted
Akim Boukhelif
Contributor
April 18, 2023

It seems possible.

DEPLOYMENT TYPE
CLOUD
PRODUCT PLAN
PREMIUM