The Atlassian Community Forums are currently in read-only mode. We will be relaunching on a new platform on September 22 (read more here). We apologize for the extended downtime. For concerns or questions, please email communitymanagers@atlassian.com. See you on the other side, on the new Atlassian Community Forums! :)

×

Forums

Articles
Create
cancel
Showing results for 
Search instead for 
Did you mean: 

Card's time in column incorrect

Kate Reeder
Contributor
January 14, 2025

Any idea what might be causing this? We are using Jira software through the cloud on a company managed, kanban project, I am the org admin. When we hover on the card on the board, it shows 7 days in column, but the status was only changed 22 hours ago, which is confirmed when we look at the history in the ticket. This kanban column only has one status aligned with the column.

why would the card show erroneous days in column? Images below.

card shows days in column.pngticket history shows hours in status.png

2 answers

1 accepted

Comments for this post are closed

Community moderators have prevented the ability to post new answers.

2 votes
Answer accepted
Trudy P Claspill
Community Champion
January 14, 2025

Hello @Kate Reeder 

Was that issue ever previously in that status/column, or is this the first time it has been there?

Bill Sheboy
Rising Star
Rising Star
Rising Stars are recognized for providing high-quality answers to other users. Rising Stars receive a certificate of achievement and are on the path to becoming Community Champions.
January 14, 2025

Yes, and...from the documentation:

If you move an issue to a column where it's previously been, the indicator provides the cumulative number of days that the issue has been in that column.

For example, you move an issue to the In progress column, and it stays there for two days.

You then move the issue to the Code review column, and it stays there for one day.

During code review, you receive feedback, which requires more development work. So, you move the issue back to the In progress column, and it stays there for one day.

In this example, the dots will reflect the cumulative value — which was three days — that the issue was in the In progress column.

 

https://support.atlassian.com/jira-software-cloud/docs/customize-cards/#Using-days-in-column

 

UPDATED: to show the Jira Cloud documentation information.

Like # people like this
Kate Reeder
Contributor
January 15, 2025

Thank you @Trudy P Claspill and @Bill Sheboy!! This explains it! 

Like # people like this
0 votes
Ashish Bijlwan
Rising Star
Rising Star
Rising Stars are recognized for providing high-quality answers to other users. Rising Stars receive a certificate of achievement and are on the path to becoming Community Champions.
January 14, 2025

Hi @Kate Reeder Image is not attached, please could you attach for history

Ashish Bijlwan
Rising Star
Rising Star
Rising Stars are recognized for providing high-quality answers to other users. Rising Stars receive a certificate of achievement and are on the path to becoming Community Champions.
January 14, 2025

Thank you for attaching the image

TAGS
AUG Leaders

Atlassian Community Events