Hi, I am a new user to Jira. I have added the fields Actual Start and Actual End to my Tasks but was not able to update them. After selecting the dates, they are not saved and always revert to None.

Any advice will be appreciated. Thanks

 

1 answer

1 vote
Kristin Lyons
Rising Star
Rising Star
Rising Stars are recognized for providing high-quality answers to other users. Rising Stars receive a certificate of achievement and are on the path to becoming Community Leaders.
March 1, 2022

When you look at the history of the issue is there anything that is reverting the changes?  What types of fields are being used (just date pickers or date:time pickers or a third party plugin field)?

Er Hwee Lin
I'm New Here
I'm New Here
Those new to the Atlassian Community have posted less than three times. Give them a warm welcome!
March 3, 2022

Hi, thanks for replying.

I dont think there is any history in the issue that is reverting the changes. This is the first time I am using this field.

The Acutal Start and Actual End are the Custom Fields (already defined in Jira). The Type is date:time picker. (see below)

Thank you

image.png

Konstantinos Sotiriou
I'm New Here
I'm New Here
Those new to the Atlassian Community have posted less than three times. Give them a warm welcome!
April 24, 2023

You also have to modify the hour to take the change.

Like # people like this
Ashton Gideon
I'm New Here
I'm New Here
Those new to the Atlassian Community have posted less than three times. Give them a warm welcome!
November 30, 2023

This was exactly my issue. The hour slot looks predefined and it wasn't apparent it needed to be edited. Thank you!