Cannot close the Sprint even though jira tkt and all of its subtasks are closed. No other option seen (screenshot).
I donot want to remove tkt from the sprint.
Kindly advice?
I was able to resolve this issue. I had to go to all apps board and found a subtask, that was not assigned to any parent tkt. Somehow this subtask was separated from its parent tkt. But system was still considering it as a subtask of that main tkt in current sprint. Deleting the subtask, enabled me to close the sprint. Finding that "orphaned" subtask led me to see that it didnot have a parent tkt linked.