Someone please help! No matter what i do, I cannot get the 'create sprint' button to appear on my backlog. I've tried/done the following:
- Created backlog
- Simplified project filter to just the project name
- Selected Add field rank ASC
- Ensured I have admin permission and double-checked 'manage sprints' is set up
What am I missing??
Hi @James Peck
If this is a Next-Gen Project - ensure you've activated sprints:
If this is a Classic Project - I'm pretty sure "Create Sprint" is on the Scrum board by default. A simple check is whether your board is a Scrum or Kanban board - to check this you can either:
^ Check these as a first step. If it is a Kanban Board, you'll need to create a new board as it's not possible to change the a Classic board's type.
If you do have the "Create Sprint" button and it's just greyed out even with all the above changes, let us know :). A screenshot would also be useful here if this is the case!
Ste