The Atlassian Community Forums are currently in read-only mode. We will be relaunching on a new platform on September 22 (read more here). We apologize for the extended downtime. For concerns or questions, please email communitymanagers@atlassian.com. See you on the other side, on the new Atlassian Community Forums! :)

×

Forums

Articles
Create
cancel
Showing results for 
Search instead for 
Did you mean: 

Can the sprint assign to an Epic update when the Due Date gets changed?

Mohammed Abdul Mannan
I'm New Here
I'm New Here
Those new to the Atlassian Community have posted less than three times. Give them a warm welcome!
April 26, 2023

Hi,

I would like to have an automation for this issue. When a due date is changed, can it automatically change the sprint value based on the date.

Any help on this will be highly appreciated.

1 answer

Comments for this post are closed

Community moderators have prevented the ability to post new answers.

0 votes
Mark Segall
Community Champion
April 26, 2023

Hi @Mohammed Abdul Mannan and welcome to the community!

No (at least not natively).  The challenge is that you need to be able to query what simply isn't possible... You want a result of a sprint based upon the due date being greater than sprint start and less than sprint end.  Jira queries are only designed to return issues.

I'm not sure this is possible with marketplace apps either because I don't see any option in the API to get this information because each available call requires a known sprint ID.