Forums

Articles
Create
cancel
Showing results for 
Search instead for 
Did you mean: 

Can the Structure Gantt roll up the Gantt finish date based on a custom field

Surekha Gupta
Contributor
May 10, 2023

Can the structure Gantt use a custom field called "Code complete Target date" to roll up to an initiative's calculated Gantt Finish Date rather than the "end Date"?

1 answer

1 accepted

1 vote
Answer accepted
David Niro
Atlassian Partner
May 11, 2023

Hello @Surekha Gupta ,

If "Code complete Target date" is a date field and you have Treat Parent Issues as Groups option enabled, this should work.

Hope this helps!

Best,
David

Surekha Gupta
Contributor
May 12, 2023

Thank you. Although it did not quite point me to the "manual scheduling configuration", the link you provided gave me a clue that I needed to configure the scheduling section. With this, I was able to make my Finish Date to align with my custom date.

Like • 2 people like this

Suggest an answer

Log in or Sign up to answer