Can the structure Gantt use a custom field called "Code complete Target date" to roll up to an initiative's calculated Gantt Finish Date rather than the "end Date"?
Hello @Surekha Gupta ,
If "Code complete Target date" is a date field and you have Treat Parent Issues as Groups option enabled, this should work.
Hope this helps!
Best,
David
Thank you. Although it did not quite point me to the "manual scheduling configuration", the link you provided gave me a clue that I needed to configure the scheduling section. With this, I was able to make my Finish Date to align with my custom date.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Online forums and learning are now in one easy-to-use experience.
By continuing, you accept the updated Community Terms of Use and acknowledge the Privacy Policy. Your public name, photo, and achievements may be publicly visible and available in search engines.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.