Can't group by sprint in jira plans

Ron Aisen
Contributor
November 6, 2025

Hi I would like to group by my plan view to be according to relevant sprints but for some reason it always gives the unassigned sprint issues only, at first i thought maybe it's related to the filter but I see that it doesn't really matter, 

image.pngimage.png

 

If Im trying to do it by releases it works fine but by sprints it's not grouping it, any ideas?

image.png

1 answer

1 accepted

1 vote
Answer accepted
BHUSHAN PATIL
Rising Star
Rising Star
Rising Stars are recognized for providing high-quality answers to other users. Rising Stars receive a certificate of achievement and are on the path to becoming Community Leaders.
November 6, 2025

Hi Ron Aisen,

If your Plan is sourcing issues directly from a project or a filter, it can't associate issues with sprint data. This results in all items being grouped under Unassigned when grouped by Sprint.

Solution: - Use a Scrum board as your issue source

  1. Create or select a Scrum board that reflects the sprints you’re using.
  2. Go to Plan → Manage views → Issue sources.
  3. Remove project/filter sources, and instead add the Scrum board as the issue source.
  4. Refresh and set Group by → Sprint in your view settings.
  5. Issues should now group under their correct sprints, not “Unassigned”.

Regards,
Bhushan Patil

Ron Aisen
Contributor
November 9, 2025

Amazing Thank you :)

This was very helpful!