Can I use the Release Burndown chart retroactively? For example I have four prior sprints and a current sprint. Can I add stories/tasks, from my four prior sprints, to a release and then generate a Release Burndown chart?

When I tried this in JIRA I see the my active sprint in the Release Burndown report but my four prior sprints are absent. The JIRA Labs parallel sprints feature was enabled when I defined my release and was subsequently is disabled in an effort to get my prior sprints into my Release Burndown report.

1 answer

0 votes
Deleted user June 1, 2015

In my experience, the Release Burndown chart will only calculate the Stories included in an Active Sprint that is configured on that current board.