Can I pull a report of all the tickets ever created for a project?

Debi Lee
I'm New Here
I'm New Here
Those new to the Atlassian Community have posted less than three times. Give them a warm welcome!
August 6, 2015

Can I pull a report of all the tickets ever created for a project? Could this then be imported to another user's JIRA account?

2 answers

1 accepted

1 vote
Answer accepted
Nic Brough -Adaptavist-
Rising Star
Rising Star
Rising Stars are recognized for providing high-quality answers to other users. Rising Stars receive a certificate of achievement and are on the path to becoming Community Champions.
August 6, 2015

Well, sort of.  If you have less than 1000 issues in the project, you can export a good swathe of the data to csv and import it from that, or even more clever stuff.

But if you want a complete project, you'll want to take a full xml backup and then use "project import" to pull that one project into the target JIRA

0 votes
Debi Lee
I'm New Here
I'm New Here
Those new to the Atlassian Community have posted less than three times. Give them a warm welcome!
August 6, 2015

Thank you!