The Atlassian Community Forums are currently in read-only mode. We will be relaunching on a new platform on September 22 (read more here). We apologize for the extended downtime. For concerns or questions, please email communitymanagers@atlassian.com. See you on the other side, on the new Atlassian Community Forums! :)

×

Forums

Articles
Create
cancel
Showing results for 
Search instead for 
Did you mean: 

Can I link sub-tasks when I create them?

Nick Menere
Rising Star
Rising Star
Rising Stars are recognized for providing high-quality answers to other users. Rising Stars receive a certificate of achievement and are on the path to becoming Community Champions.
October 15, 2017

I want to create 3 sub-tasks - A, B & C so that A blocks B and B blocks C.

Am I able to do this?

1 answer

1 accepted

Comments for this post are closed

Community moderators have prevented the ability to post new answers.

0 votes
Answer accepted
Nick Menere
Rising Star
Rising Star
Rising Stars are recognized for providing high-quality answers to other users. Rising Stars receive a certificate of achievement and are on the path to becoming Community Champions.
October 15, 2017

This can be done by linking the sub-tasks when they are created to the "Most recently created issue" (in this case, the previous sub-task).

Note. You need to use the full "Create issue" action to create sub-tasks so that you can edit other fields.

You rule will look something like: