  • Can I change the "A forecast cannot be shown until at least 3 sprints have been completed" limit for epic burndown?

Can I change the "A forecast cannot be shown until at least 3 sprints have been completed" limit for epic burndown?

Iakiv Kramarenko September 2, 2014

I want the forecast in epic burndown to be available earlier that 3 sprints. Can this be configured somethow?

1 answer

1 accepted

1 vote
Answer accepted
Nic Brough -Adaptavist-
Rising Star
Rising Star
Rising Stars are recognized for providing high-quality answers to other users. Rising Stars receive a certificate of achievement and are on the path to becoming Community Leaders.
September 2, 2014

No, it needs some data to work with before it can begin to give you anything usable, and the limit is codeded into the Agile plugin