Calculate subtasks points on burndown

Vianna
I'm New Here
I'm New Here
Those new to the Atlassian Community have posted less than three times. Give them a warm welcome!
September 21, 2018

I need in the graphical burndown to appear the value of the points of each subtask created within a History.

Because I have several histories with many subtasks and not being displayed in the graph the subtasks points when completed.

 

Can someone help me please?

Tks

Vianna

1 answer

0 votes
Nic Brough -Adaptavist-
Rising Star
Rising Star
Rising Stars are recognized for providing high-quality answers to other users. Rising Stars receive a certificate of achievement and are on the path to becoming Community Leaders.
September 22, 2018

This is wrong, so you can't do it.

When you take a story into a sprint, you are saying "we will complete this during the sprint".  Burn-down is based on completion of what you committed to, not parts of it.  So it's nonsense to have a sub-task count.  Either the story is done (points burn down) or it is not (points are not burned down).

There are uses for points on sub-tasks, but because they're irrelevant to burn-down, even if you found/wrote code to sum them up to their parents and/or get them into other reports, they're still useless to a burn-down chart.