Hi all,
I am trying to import a CSV to which includes backdated creation dates for some issues & the dates that the issues have been completed. From looking through other community questions and answers on this forum, I have tried to format my CSV and the way that Jira will read the dates correctly, however no matter what I try, it always shows up with an error:
Image one: trying dates with dd/MMM/yy h:mm format, no quotes
Image two: trying dates with dd/MMM/yy h:mm format, quotes
Can anyone tell me why no matter which date format & csv format I use, it always gives an error?
Many thanks
Hi @Amelia King , welcome to the Atlassian Community!
I would check how the export format looks on issues created in Jira, then match it in the import file
Hi Amelia - Welcome to the Atlassian Community!
I have found that if you set the format to YYYY-MM-DD that should work. Be sure to set the format in the CSV itself as well as the format in the import tool.