Burndown chart offers only Original Time Estimate

Alex Reznik
I'm New Here
I'm New Here
Those new to the Atlassian Community have posted less than three times. Give them a warm welcome!
July 13, 2021

Hello, 

In the Burndown chart report (and Burnup), the system offers only Original Time Estimate as a measure of remaining work, thus time entries do not adjust the graph.  The remaining work is reduced only when an issue is complete vs. ongoingly as work is logged. 

If that's how burndown/up is "supposed" to work, is there a way to monitor remaining work per task and overall on an ongoing basis?

Please advise. 

 

Thank you.

 

Best regards,

Alex

1 answer

0 votes
Nic Brough -Adaptavist-
Rising Star
Rising Star
Rising Stars are recognized for providing high-quality answers to other users. Rising Stars receive a certificate of achievement and are on the path to becoming Community Leaders.
July 13, 2021

That's what a burndown is supposed to do - you burn down when an issue is complete, not part way through.