Burndown chart not reflecting burn hours

AADIRanjan
I'm New Here
I'm New Here
Those new to the Atlassian Community have posted less than three times. Give them a warm welcome!
June 11, 2018

I'm new for Jira. My administrator have set burn down chart against story points. In Sprint1 have (mix of stories and Tasks).  Team members have assigned tasks. We put original effort in hours against tasks. We are logging effort in hours too.

Let's take below example

Task A was Original estimated 3h.  I worked on this task and log work as 2h and changes status "Done". When I'm going to see burn down chart it's not reflecting.

 

Is burndown chart works against stories only?

1 answer

1 vote
Nic Brough -Adaptavist-
Rising Star
Rising Star
Rising Stars are recognized for providing high-quality answers to other users. Rising Stars receive a certificate of achievement and are on the path to becoming Community Champions.
June 11, 2018

Burndown works off the "done" column in the board.  The issue type does not matter, just what is in the last column.