The Atlassian Community Forums are currently in read-only mode. We will be relaunching on a new platform on September 22 (read more here). We apologize for the extended downtime. For concerns or questions, please email communitymanagers@atlassian.com. See you on the other side, on the new Atlassian Community Forums! :)

×

Forums

Articles
Create
cancel
Showing results for 
Search instead for 
Did you mean: 

Burndown chart is incorrect

Frances Moncrief
Contributor
March 12, 2021

Example:  Sprint contains 10 backlog items.  7 are completed during sprint. The remaining 3 are "In Progress".  The 3 "In Progress" items are returned to the backlog at the end of the sprint.  When I view the sprint burndown chart, the 3 items are showing in the chart as completed with a status of "In Progress".  This seems like a bug... but perhaps it is another issue.  Any ideas?

1 answer

Comments for this post are closed

Community moderators have prevented the ability to post new answers.

0 votes
Trudy P Claspill
Community Champion
March 12, 2021

Hello @Frances Moncrief 

Are you working with a Next Gen project or a Classic project?

Can you show us the burndown chart where it is showing the In Progress item as completed in the sprint?