Forums

Articles
Create
cancel
Showing results for 
Search instead for 
Did you mean: 

Burndown chart - Status "not closed"

Peter Karam
I'm New Here
I'm New Here
Those new to the Atlassian Community have posted less than three times. Give them a warm welcome!
August 21, 2022

We have a scenario where issues that are completed in a sprint need to be kept at "Ready for UAT" status , and not to be closed. That being said, we are not able to make use of Burndown chart.

Is there a way to configure the burndown chart to depend on a status different from "Closed/Done" (i.e. "Ready for UAT") ?

or any other advice?

1 answer

1 vote
Rik de Valk
Community Champion
August 21, 2022

Hi @Peter Karam ,

Yes that is possible. The Scrum board will consider and status that is mapped to the last column in your Board as done. 

So you can map Ready for UAT to the last column and your burn down will act accordingly.

Have a nice day! 

Suggest an answer

Log in or Sign up to answer