The Atlassian Community Forums are currently in read-only mode. We will be relaunching on a new platform on September 22 (read more here). We apologize for the extended downtime. For concerns or questions, please email communitymanagers@atlassian.com. See you on the other side, on the new Atlassian Community Forums! :)

×

Forums

Articles
Create
cancel
Showing results for 
Search instead for 
Did you mean: 

Bulk edit Ranks in Portfolio for JIRA cloud

MBeri
April 27, 2020

Hi All,

I am using Portfolio for JIRA on cloud and I find it extremely difficult to prioritize tickets/changing ranks by drag and drop one ticket at a time. Just note, my plan has over 400 stories..

Is there an easier and faster way to do this?

 

Thanks

 

2 answers

1 accepted

Comments for this post are closed

Community moderators have prevented the ability to post new answers.

0 votes
Answer accepted
Lachlan G
Atlassian Team
Atlassian Team members are employees working across the company in a wide variety of roles.
May 19, 2020
MBeri
May 19, 2020

yes, really happy to see that its available in the new release.

0 votes
Elad Ben-Noam
Contributor
April 28, 2020

@MBeri - I am not familiar with a way to perform it in bulk with Portfolio Cloud version.

It is available on Portfolio for Jira Server and a new Portfolio/roadmaps should arrive soon for cloud, it might include bulk ranking.

 

For now when you want to rank I would suggest you to filter the plan as much as possible: keeping only "To do" issues and removing in progress/done issues. In case you are working with different teams, filter only the team's issues and then rank.

MBeri
April 28, 2020

@Elad Ben-Noam  There are very limited filters available. and even sorting is not enabled on all fields. Well, how can we get these basic features added to their backlog?

Elad Ben-Noam
Contributor
April 29, 2020

@MBeri , Not so sure what you mean by that.

You have "More" button in the filters row to enable more filtering, see image.

ans_portfolio.png

Sorting is another issue, and you are correct it's a bit limited inside the portfolio.

Regarding the backlog, on the board settings that you are using you can add "quick filters" with any filter JQL query you want.