Blue Status vs Grey Status?

Lior Broshi
Contributor
January 21, 2020

Given a status in a column - I see two colors; blue and grey - what is the difference?

 

b75e6e4a-83b7-4959-a910-9fa7ffce1e36.png

2 answers

3 votes
Jack Brickey
Community Champion
January 21, 2020

Grey = To Do

Blue = In Progress

Green = Done

these are status "categories" used w/in Jira for various functions.

Gary
I'm New Here
I'm New Here
Those new to the Atlassian Community have posted less than three times. Give them a warm welcome!
January 29, 2020

Question:  I have 5 statuses in the done column. 4 are Green and 1 is Grey (Accepted).  Any idea why this is and can I change it?  We use Jira Cloud if that matters...

Thanks

Like Craig Brown likes this
2 votes
Nic Brough -Adaptavist-
Rising Star
Rising Star
Rising Stars are recognized for providing high-quality answers to other users. Rising Stars receive a certificate of achievement and are on the path to becoming Community Leaders.
January 21, 2020

It's the status category - blue is in-progress, gray means t0-do (or, sometimes, that you have not given the status a category).  Go to Admin -> issue -> status to change them.