BigPicture - Removing dotted red lines on Gantt Chart

Logan Clemons
June 20, 2019

red-lines.PNG

 

I'm trying to remove this dotted red line on this gantt chart. Is there any way to remove this without an additional plugin?

1 answer

0 votes
Patryk-SoftwarePlant
Rising Star
Rising Star
Rising Stars are recognized for providing high-quality answers to other users. Rising Stars receive a certificate of achievement and are on the path to becoming Community Champions.
December 5, 2019

Hi Logan,

The red-dotted line (orange-dotted in newer versions) indicates the position of the parent task after it is recalculated based on its children. This happens when manual mode is enabled or the issue is locked.

You can read more about task modes here.

Cheers,

Patryk