Hi, I do NOT want to autoschedule issues in BigGantt. Is there a way to switch this feature off ? Globally or even for each Gantt?
Currently I can indicate manual scheduling within in a particular Gantt, it then adds a manual scheduling icon to each issue in the Gantt. But when a new issue is created in JIRA and I re-sync the Gantt, that new issue does not have the manual scheduling flag
. So I have to see and correct BEFORE doing any scheduling changes. This is FAR to dangerous for us.
Community moderators have prevented the ability to post new answers.
Hi,
Please switch off the auto scheduling in DATA -> SCHEDULING -> manual.
Also make sure the Gantt config synchronization and "recalculate parents" is off.