We are following two weeks sprint . The planning is done bi mothly so we plan ahaed for two months .. Is there a way I can pull Bi-Monthly burn down chart so that management can see the Planned items for B- MOnthly VS delivered and scope added / removed etc .. Please suggest the best possible solution in Jira for this report .
As far as I know, Jira's burndown report or burndown gadget do not support this, but can try to achieve this with a plugin (app) from Atlassian Marketplace,
If you are open to trying a plugin, our Great Gadgets app offers a Release Burndown Burnup Chart gadget that will let you display the burndown you need.
This gadget can also display forecast (based on velocity) and let you set milestones (custom dates).
It supports custom time intervals, so you will be able to configure it to use intervals of 8 weeks (2 months).
Danut.
Thanks @Danut M _StonikByte_ , I have explored this gadget . But I think its costing around 1500 $ which is bit expensive. And so I am looking for other possible options.