In the SM project, I have turned on the below automation rule.
"When a low risk change management request is in review → then move request to approved"
Now, when I create a change request and assign the risk as "low", the ticket status automatically moves from "awaiting CAB approval" to "Awaiting implementation" - As expected.
But, when we see the audit logs, there are two , 1 with success and 1 with "some errors"
Success states that -
Issue approval has been completed for action
Approve
Some errors states that -
There was a problem performing approve/decline in Jira:
Issue was in a status where approval was not required
How to resolve this? Please help
Hi @Sridevi Mugundan , my first thought is that it is associated with the workflow for the triggering issue.
questions: