Automation related to subtask summary

mlangtry
I'm New Here
I'm New Here
Those new to the Atlassian Community have posted less than three times. Give them a warm welcome!
August 17, 2023

Hello there

I am trying to create a automation rule that generate a subtask called 'QA' when an issue is moved to the Active Sprint and it doesn't already have a subtasked called 'QA'.

So the trigger is the change of the Sprint, and the conditions are:

1. the (new) sprint is the currently Active Sprint

2. there is no other subtask called 'QA' under that issue

The action is to create a new subtask called 'QA'.

I've created the below rule and it didn't work. It generated a subtask called 'QA' in the Active Sprint even though there was one under the issue already. 

Please share your thoughts.

Thanks

Screenshot 2023-08-17 at 5.43.27 pm.png

 

2 answers

1 accepted

1 vote
Answer accepted
Marco Brundel
Rising Star
Rising Star
Rising Stars are recognized for providing high-quality answers to other users. Rising Stars receive a certificate of achievement and are on the path to becoming Community Leaders.
August 17, 2023

Hi @mlangtry ,

Welcome to the Atlassian Community.

In a similar use case I used a Related issues condition instead of a Compare two values. Is this an option for you?

Regards, Marco Brundel

Screenshot 2023-08-17 at 10.08.41.pngScreenshot 2023-08-17 at 10.07.26.png

0 votes
mlangtry
I'm New Here
I'm New Here
Those new to the Atlassian Community have posted less than three times. Give them a warm welcome!
August 17, 2023

Thank you so much @Marco Brundel ! It works! 