Automatically move dependant task to next Sprint

Patrick
I'm New Here
I'm New Here
Those new to the Atlassian Community have posted less than three times. Give them a warm welcome!
July 1, 2018
I have tasks set up under an Epic for UX, UI, HTML, DEV and the tasks must be completed in that order. When one of the tasks is delayed, this should push the next task into the next Sprint. Each sprint is 10 days and each task is estimated in days. So for example, if a ux task is 5 days and UI task is 5 days, and UX task is delayed by 3 days, then UI task should be pushed into the next Sprint. What's the best way to do this without having to manually move tasks each time there is a delay?

1 answer

0 votes
Ollie Guan
Community Champion
July 1, 2018

Hi @Patrick,

I think a sprint should include a complete deliverable user increment.

Therefore, I suggest that Epic should break up to Story, while the specific engineering tasks of UX, UI, HTML, DEV should belong to the Story.

If any of the tasks in the Story are not completed, at the end of the Sprint, the entire Story will be moved back to the Backlog waiting for the redefined priorities to be sorted into the next Sprint.

Hope this helps.