The Atlassian Community Forums are currently in read-only mode. We will be relaunching on a new platform on September 22 (read more here). We apologize for the extended downtime. For concerns or questions, please email communitymanagers@atlassian.com. See you on the other side, on the new Atlassian Community Forums! :)

×

Forums

Articles
Create
cancel
Showing results for 
Search instead for 
Did you mean: 

Automatic adjustment of due dates

Michał Fulara
I'm New Here
I'm New Here
Those new to the Atlassian Community have posted less than three times. Give them a warm welcome!
March 25, 2015

Hi,

Is it somehow possible to set an automatic adjustments of due dates of linked issues?

e.g. I have a task with 3 sub-tasks, each concecutive one is dependent on the previous (blocked by) and their due dates are set accordingly. There is a 1 week delay on the first sub-task and I change it’s due date to 1 week later. I would like for each issue linked to it to automaticaly adjust their due dates (each move its due date by 1 week forward).

Could this be done?

1 answer

Comments for this post are closed

Community moderators have prevented the ability to post new answers.

Post a new question

0 votes
Jobin Kuruvilla [Adaptavist]
Rising Star
Rising Star
Rising Stars are recognized for providing high-quality answers to other users. Rising Stars receive a certificate of achievement and are on the path to becoming Community Champions.
March 25, 2015

You will have to do some coding to do this. Write a listener that catches the due date changes and updates the linked issues.