The Atlassian Community Forums are currently in read-only mode. We will be relaunching on a new platform on September 22 (read more here). We apologize for the extended downtime. For concerns or questions, please email communitymanagers@atlassian.com. See you on the other side, on the new Atlassian Community Forums! :)

×

Forums

Articles
Create
cancel
Showing results for 
Search instead for 
Did you mean: 

Auto alignment due date between linked tasks

Degio
I'm New Here
I'm New Here
Those new to the Atlassian Community have posted less than three times. Give them a warm welcome!
October 11, 2022

Hi, I have a common proect managment problem to solve but I can't find the way.

I need an automation that aligns due date between linked tasks (subtasks with parent or linked iessues with blocks connections). 

...Any advice?  There's aready this kind of automation available?

1 answer

1 accepted

Comments for this post are closed

Community moderators have prevented the ability to post new answers.

0 votes
Answer accepted
Mark Segall
Community Champion
October 11, 2022

Hi @Degio and welcome to the community!

You could do something like this:

  • TRIGGER: Field Value Changed (Due Date)
  • BRANCH: Linked Issues (Blocks)
    • ACTION: Edit Issue
      • Due Date
  • BRANCH: Parent
    • ACTION: Edit Issue
      • Due Date
Degio
I'm New Here
I'm New Here
Those new to the Atlassian Community have posted less than three times. Give them a warm welcome!
October 11, 2022

Hi Mark. Thanks so much. 

I just tried your solution and is perfectly working ;)

Thanks and best regards.

 

Degio

Like Mark Segall likes this